The Chad–Cameroon Pipeline Project: Some Thoughts about the Legal Challenges and Lessons Learned from a World Bank-financed Large Infrastructure Project

Mohammed A. Bekhechi

in Energy Networks and the Law

Published in print February 2012 | ISBN: 9780199645039
Published online May 2012 | e-ISBN: 9780191738647 | DOI: http://dx.doi.org/10.1093/acprof:oso/9780199645039.003.0005
The Chad–Cameroon Pipeline Project: Some Thoughts about the Legal Challenges and Lessons Learned from a World Bank-financed Large Infrastructure Project

More Like This

Show all results sharing this subject:

  • Environment and Energy Law

GO

Show Summary Details

Preview

The Chad–Cameroon Project (CCP) was designed to develop oil fields at Doba in southern Chad and to construct a 1070 km pipeline from the Doba oil fields to oilloading facilities off Cameroon's Atlantic coast in Kribi, including all ancillary facilities, pumping stations, and other related infrastructures. It was, at the time of its preparation, the single largest oil and infrastructure project developed in that part of the world. This chapter discusses the legal framework for the inception and operation of the CCP, environmental and social aspects of the CCP, legal issues raised and faced by the CCP, and lessons learned from the CCP project.

Keywords: pipeline projects; oil field development; southern Chard; Doba oil fields

Chapter.  12345 words. 

Subjects: Environment and Energy Law

Full text: subscription required

How to subscribe Recommend to my Librarian

Buy this work at Oxford University Press »

Users without a subscription are not able to see the full content. Please, subscribe or login to access all content.