slack


Show Summary Details

Quick Reference

(in critical path analysis)

The difference between the latest time and the earliest time at a vertex (node) in an activity network. It represents the allowable delay at that point in the process which would not delay the overall completion. The slack will be zero for critical events.

Subjects: Mathematics.